Over the past few weeks, we’ve continued moving through key site preparation milestones, even as heavy rain moved through Winnipeg. We are now at the stage where the site is getting fully ready for the foundation work ahead.

What We Completed

We’re pleased to share that despite a wet stretch of weather, progress on site hasn’t slowed down:

  • Tree removal is complete
  • Site excavation is underway
  • Heavy rainfall throughout the month has been managed without delay to the schedule

While weather like this can look concerning from the outside, our site team has adapted work schedules to keep things moving. Tree clearing and excavation are essential steps in preparing the site for foundation work. These activities ensure the ground is ready for the next phase of construction.

Aerial view of Six Eleven on the River and the surrounding riverside neighbourhood
Six Eleven on the River, set among the mature trees of the riverside neighbourhood

What’s Coming Next

The site is well on track to move into foundation work in the weeks ahead. Excavation work will continue to prepare the site for foundation construction.

Foundations

Following excavation, foundation work is expected to get underway, building on the piling already completed for Units 6, 7, 8, and 9.

As with all construction schedules, timelines can shift due to weather and trade availability. We’ll continue sharing updates as milestones are reached so you can follow progress with confidence.

Excavation underway at the Six Eleven on the River construction site
Excavation underway at Six Eleven on the River

This project is designed as a rare offering: private, house-like living paired with the simplicity of a managed community — an appealing option for buyers looking for Winnipeg detached homes with the privacy and prestige of Wellington Crescent.

We’ll post the next update soon, including progress on excavation and the start of foundation work.